Project Progress
Hythe by Botanica
Environmental Impact Assessment ( EIA ) Construction Permit
6.94%

It is expected to be completed in 20 March 2026

  • 16.27% Structure Works
  • 100% Footing & Underground Works
  • 100% Pilling Works

Updated: 20 March 2026

Project Progress
Hythe by Botanica
Environmental Impact Assessment ( EIA ) Construction Permit
6.94%

It is expected to be completed in 20 March 2026

  • 16.27% Structure Works
  • 100% Footing & Underground Works
  • 100% Pilling Works

Updated: 20 March 2026

By continuing to use this website you agree to the use of cookies according to our Privacy Policy.

Cookie Consent Preferences

Cookies are little bits of textual information which are used by the website to enhance user experience. Accept all cookies or choose which categories you want to allow.

Accept All
Manage Consent Preferences
  • Mandatory Cookies
    Always Active

    These are necessary for the basic functioning of the website and for its correct performance.

  • Analytics Cookies / Advertising and Social Media Cookies

    Analytics Cookies
    These enable use of the website to be measured, in order to ensure its proper performance and to improve its functioning.

    Advertising and Social Media Cookies
    These are used to display and measure ads which are relevant to our users, as well as enabling interaction with social media. Data may be shared with companies outside of Botanica Luxury Villas.
    Cookies Details

Save My Preferences